Skip to main content

Set how risk levels are calculated

Learn how to set the probability ranges and the level of each cell in the risk level matrix that Loctax uses.

J
Written by Jelle Loos

Prefer to read or print? Download this guide as a PDF.

Steps

  1. Open Risks. On the dashboard, go to the risk level matrix, and select the settings icon.

  2. Under Probability ranges, set where each probability of loss column starts and ends, for example from 25 to 50 percent. A value on a boundary goes in the higher column.

    Configure risk levels: the probability ranges

  3. Select any cell in the matrix to choose its risk level, from Very low to Very high, for each combination of impact and probability.

    A matrix cell with the list of risk levels

  4. Below the matrix, Loctax lists the risks whose level changes, so you can check the effect before you save.

    The matrix after the change, and the risk that would change level

  5. Select Save. To go back to the standard matrix, select Reset to default.

Good to know

  • Saving updates the level of every risk, including risks you can't see.

Related articles

Did this answer your question?